Rosemary Street Improvements

About the Project

Commerce City is proposing the Rosemary St. Widening Project between East 86th Avenue and East 81st Place. The city is evaluating the environmental and right-of-way impacts for the improvements and will develop preliminary and final design along this 0.6 mile stretch. This project compliments widening and improvements to the E. 88th Avenue and Rosemary St. intersection being completed as part of the City’s E. 88th Avenue Improvements Project.

The Rosemary Street project was identified as a priority improvement in the city’s recently-adopted Irondale Neighborhood and Infrastructure Plan, with partial funding already identified in the city’s five-year Capital Improvements and Preservation Plan. 

Fast Facts

English: Project Factsheet 

Spanish: Project Factsheet 

Status: Design 90% complete
Construction begins: Spring 2022
Expected completion: Early 2023

Project Details

Widen Rosemary Street to an arterial roadway section from 80th Avenue to 88th Avenue to allow for better and safer traffic flow. The design will include a 4-lane road from 88th Ave to 85th Ave where the road will taper to a 3-lane roadway including one lane in each direction and a wider median turn lane. It also includes a 6’ sidewalk and an 8’-10’ multiuse trail running the length of Rosemary Street.

Public Comment Period

The city is seeking feedback on improvement plans for Rosemary Street in the Irondale neighborhood. For more information on these projects and to provide feedback, visit C3RoadwayImprovements.com. Comments will be accepted through July 25.

Construction Schedules and Project Budgets

  • Preliminary design completed: Summer 2020
  • Final design: Winter 2020
  • Right-of-Way & Utilities: 2021
  • Begin Construction: Spring 2022

Contact Us

For information about core city sidewalks, E. 88th Avenue, Irondale drainage improvements, Rosemary St. widening, and land acquisition/right-of-way purchase:
Diana Trettin
Project Manager
Email